Ofgem published its Curate consultation on 29 July 2026. It proposes two significant reforms for in-scope data centres seeking a grid connection in Great Britain: a new Data Centre Commitment Fee (DCCF), proposed as a returnable financial security required from offer acceptance to energisation, and additional queue management milestones requiring developers to demonstrate genuine project progression.
This article updates our previous article UK grid connections reform: impact on data centres and demand connections.
Key takeaways
- The measures are proposed to apply to data centre connections at both transmission and distribution-level and the data centre component of hybrid projects. They are relevant to those with an existing connection agreement or offer, future connection applications and projects changing their technology type to a data centre (e.g. from battery storage). Developers across these categories should assess their potential exposure now.
- Data centres of at least 40 MW would be required to secure £237,500 - £712,500 per MW of requested capacity at offer acceptance (equivalent to up to £71.3 million for a 100 MW project), with no refund until energisation. The proposed fee is significantly higher than equivalent fees in other jurisdictions and, for projects with later connection dates, could tie up security for almost 10 years (without accounting for any further connection delays). Investors and developers will need to factor this into project economics and financing structures.
- The DCCF will create further timing pressures for developers seeking to sell or obtain funding for powered land once a connection offer is received and connection terms are known. Developers will have a limited window to put in place significant financial security following offer acceptance, at a point when sale or funding arrangements may not previously have been finalised. Grace periods provide some relief for existing projects but will not eliminate this challenge.
- New queue management milestones will require data centre developers (Ofgem's preferred threshold for the new milestones is at least 10 MW rated IT load) to evidence compute offtake arrangements, procurement of long-lead electrical equipment, financial capability and technical readiness between offer acceptance and energisation. For developers not intending to self-operate, a non-binding compute offtake arrangement must be in place within just 6 months of offer acceptance; a tight deadline for developers in the early stages of project development. Failure to meet milestones risks termination of the connection agreement.
- The proposals are not yet final. Ofgem is seeking stakeholder views on the design, scale and implementation of the measures, including explicitly calling for input on key details such as the level of the DCCF. Stakeholders should consider engaging with the consultation before the 16 September deadline to ensure the reformed regime works for their business model.
The consultation closes on 16 September 2026, with decisions expected later in 2026. Please contact us if you would like to discuss the implications for your project.
Key contacts
Sarah Pollock
Partner, Head of Energy Sector, London
Dr Silke Goldberg
Partner, London and Israel Group
Sam Cundall
Partner, London
Kate Laidlow-Singh
Of Counsel, London
Oli Grabowski
Senior Associate, London
Legal Notice
The contents of this publication are for reference purposes only and may not be current as at the date of accessing this publication. They do not constitute legal advice and should not be relied upon as such. Specific legal advice about your specific circumstances should always be sought separately before taking any action based on this publication.
© Herbert Smith Freehills Kramer 2026
Stay in the know
Receive timely insights and briefings from HSF Kramer, tailored to keep you informed and ahead