On 19 August 2026, Ofgem launched a non-statutory consultation on draft licence conditions for Competitively Appointed Transmission Owners ("CATOs") and accompanying guidance (see link here). The proposed CATO-specific Section F of the electricity transmission licence sets out the regulatory framework that will govern CATOs across the full project lifecycle. The consultation closes on 16 October 2026.
The draft licence gives effect to Ofgem's previous decisions on the CATO commercial model (October 2024 and July 2025). While it draws heavily on the existing Offshore Transmission Owner ("OFTO") regime, it has been adapted for onshore assets and introduces several novel features outlined below.
Background to the CATO regime
The CATO regime introduces an "Early Competition" model for developing onshore transmission assets, a competitive tender process through which a single entity is appointed to design, finance, build and operate specific onshore electricity transmission assets. Currently onshore works are implemented by licensed transmission network owners. The CATO model is intended to drive innovation and cost efficiency while creating new investment opportunities in onshore networks.
The regime is intended to apply to network projects which are identified by the National Energy System Operator ("NESO") as being new, separable, capable within reasonable certainty of addressing a network need, and having a positive consumer benefit compared to a non-competitive approach (demonstrated by a cost benefit analysis). Ofgem will decide whether a project should be tendered, and NESO will then be responsible for running the tender process in accordance with the process set out in The Electricity (Early-Model Competitive Tenders for Onshore Transmission Licences) Regulations 2025.
Unlike the current regime for OFTOs, the CATO regime will require successful bidders to design and build the onshore transmission assets.
Key licence features
| 1. | Obligation to construct: |
|
| 2. | Revenue stream: |
|
| 3. | Post-Preliminary Works Cost Adjustment (PPWCA): |
|
| 4. | Financial Close adjustments: |
|
| 5. | Incentives: |
|
| 6. | Agreed refinancing: |
|
| 7. | End of revenue stream: |
|
| 8. | CATO of Last Resort: |
|
Timeline
Ofgem currently anticipates the following timetable for the first CATO projects:
| Date | Event |
| 16 October 2026 | Non-statutory consultation closes |
| Late 2026 | NESO to request the first project(s) for competitive tender, following the transitional Centralised Strategic Network Plan 2 (tCSNP2) Refresh |
| Early 2027 | Ofgem to publish a further update following consultation responses, followed by a statutory consultation reflecting feedback |
| 2027 | First CATO onshore competition tender expected to launch |
| TBC | First CATO licence award |
Implications for market participants
The draft CATO licence and guidance represent a material step forward in the onshore transmission competition regime, moving it into the implementation phase after a decade of policy development.
While the alignment of aspects of the CATO regime with the existing OFTO model should improve familiarity to participants already participating in offshore transmission projects, the new CATO regime represents a fundamentally different delivery profile which requires its own risk and reward assessment by developers and their funders.
Please do not hesitate to contact us if you would like to discuss the proposed CATO model.
Key contacts
Dr Silke Goldberg
Partner, London and Israel Group
Sam Cundall
Partner, London
Sarah Pollock
Partner, Head of Energy Sector, London
Paul Butcher
Director of Public Policy, London
Disclaimer
The articles published on this website, current at the dates of publication set out above, are for reference purposes only. They do not constitute legal advice and should not be relied upon as such. Specific legal advice about your specific circumstances should always be sought separately before taking any action.