The NSW Government proposes to introduce industry-specific environmental assessment requirements, new assessment guidelines and an environmental impact statement (EIS) certification regime for State significant projects. Public submissions on the proposed reforms will close on 12 February 2021.
DPIE is moving towards setting SEARs on an industry rather than a project level for SSD projects that are wholly permissible, not designated development, and not a concept development application. This reform seeks to allow DPIE and agencies to focus more on projects that have greater environmental risks or seek to depart from existing land use controls.
DPIE has released draft industry-specific SEARs for hospitals, medical centres and health research facilities, warehouses and distribution centres, and development within identified sites and precincts. These industry-specific SEARs will be finalised having regard to the submissions received through the public exhibition.
Going forward, DPIE will also prepare industry-specific SEARs for other categories of development. DPIE states that this move away from a ‘one-size-fits-all approach’ will allow for a better allocation of resources and a streamlined major project assessment.
DPIE is exhibiting proposed amendments to the Environmental Planning and Assessment Regulation 2000 (NSW) (EP&A Regulation) aimed at keeping an EIS succinct, easily understood, technically robust and reflective of community views.
In particular, the proposed amendments require an EIS and modification applications for SSD and SSI projects to be prepared having regard to the proposed SSD Guidelines and SSI Guidelines. These guidelines address issues such as:
The proposed amendments to the EP&A Regulation also include:
The proposed amendments to the EP&A Regulation also introduce a scheme that requires an EIS to be certified before being submitted. This seeks to ensure that an EIS is prepared to a high standard and that the public has greater confidence in an EIS.
The scheme is detailed in the REAPs Guidelines and involves two main aspects:
You can view the exhibited documents and make a submission on the NSW Planning Portal. You can also send a written submission to DPIE by post.
Public submissions will close on 12 February 2021.
By Peter Briggs, Partner, Tom Dougherty, Senior Associate and Zhongwei Wang, Solicitor.
We take a creative, strategic and commercial approach to environment and planning issues. If you need urgent advice or just have a general query, please contact one of us below.
Partner, Sydney
Partner, Sydney
Partner, Sydney
Partner, Sydney
Partner, Sydney
Partner, Sydney
Partner, Sydney
Partner, Sydney
The articles published on this website, current at the dates of publication set out above, are for reference purposes only. They do not constitute legal advice and should not be relied upon as such. Specific legal advice about your specific circumstances should always be sought separately before taking any action.