Energy capabilities
Deep expertise. Commercial edge.
Reforms have been proposed which signal the next step in Great Britain's (GB) evolving connections reform process and a more interventionist and strategic approach to demand connections. More proposals are expected in the second half of the year. The first phase of connections reform placed more focus on electricity generation and storage but attention is turning to the demand connections queue, particularly given the rapid growth in connection applications for large demand projects such as data centres. If implemented, the reforms can be expected to have significant impacts for projects seeking an import connection from the grid and offer new opportunities for investors in grid solutions. In this article, we unpack the proposed reforms and what they could mean in practice.
The Department for Energy Security and Net Zero (DESNZ), in its accelerating electricity network connections for strategic demand consultation published on 11 March 2026 (the DESNZ Consultation), and Ofgem, in its Demand Connections Reform Call for Input issued on 13 February 2026 (the Ofgem CfI), have outlined a programme of demand connections reform. On 16 June 2026, Ofgem published both a Summary of Responses, which sets out its initial positions on certain proposals made in the Ofgem CFI (the Ofgem SoR), and an update on the "Connect" pillar of demand connections reform (the Ofgem Connect Update).
Projects seeking a demand connection to the GB grid are facing major challenges. According to the Ofgem CfI, between November 2024 and June 2025 demand side connection applications increased sharply by over 300%, from 41 GW to 125 GW, exceeding even the highest demand forecasts, with a significant portion of the demand queue occupied by data centres.
Although the new gated connections process applies to transmission-connected demand, less onerous requirements apply to demand projects than to generation projects. Under the new process, projects that satisfy both the “ready” and “needed” criteria are eligible to receive a firm "Gate 2" connection offer. Demand projects only need to meet the "ready" criteria (ie, holding sufficient land rights or submission of a Development Consent Order application) as they are currently deemed to have automatically met the "needed" criteria. Distribution-connected demand is currently out of scope of the reformed process.
Among the projects included in the demand queue, Ofgem and DESNZ expect many to be non viable - for example, those unable to obtain planning permission or secure a final investment decision. As a result, the progression to connection for important demand projects, such as data centres needed as part of the government’s AI Growth Zones programme (see our AI Growth Zones in the UK to Promote AI Data Centre Investment article for details), is being hindered.
To address this situation and ensure that viable projects can secure timely connections and strategic projects can be prioritised, DESNZ and Ofgem propose a reform of demand-side connections.
Demand connection reform is intended to be implemented across three pillars — Curate, Plan, Connect, with DESNZ and Ofgem taking responsibility for progressing different aspects of the reforms. The Curate and Plan pillars are split into two phases, with Phase 1 expected to be in place ahead of the next connections application window and Phase 2 expected to be in place for the following connections application window. The details remain subject to further consultation.
CurateNew or strengthened queue entry and membership criteria to ensure that viable projects progress to connection |
| Ofgem-led |
Phase 1
Phase 2
|
PlanPrioritisation of strategic projects and a strategic plan for data centres |
| Government-led |
Phase 1
Phase 2
Other
|
ConnectNew approaches and connection arrangements to accelerate physical connections |
| Ofgem and Government-led |
|
The Curate pillar aims to strengthen queue entry and membership requirements to ensure that the demand queue consists only of viable projects capable of progressing to connection. Phase 1 focuses primarily on data centres and Phase 2 expands to cover wider demand types.
Ofgem set out a number of changes it is considering in relation to Phase 1 of the Curate pillar in the Ofgem CfI and provided an update on its current position in the Ofgem SoR. Further details are expected to be included in the upcoming Ofgem Curate consultation, with final decisions expected later in 2026. Government intends that Planning and Infrastructure Act 2025 (PIA) powers will be used to implement the final Curate measures. These measures would affect demand projects already in the connections queue through the G2tWQ process and successful new applicants in future connection windows, as well as any generation projects seeking to change use of their connection to demand.
Proposals under consideration include:
The Plan pillar aims to ensure that the demand connections process delivers timely connections for strategic projects, while also supporting wider Government priorities such as economic growth and decarbonisation. Government intends to use its PIA powers to introduce mechanisms to allow NESO and the network companies to prioritise projects identified by Government as having strategic network importance.
The policies under consideration in the DESNZ Consultation (Government response awaited) include:
The Connect pillar aims to accelerate and increase the number of physical grid connections for demand projects, and to ensure the system can operate effectively and securely even as large demand loads increase. The policies under consideration include:
If you would like to understand more about what demand connection reforms mean for you or your business, please do not hesitate to get in touch.
Junya Ohashi, a lawyer seconded from Nishimura & Asahi in Japan, contributed to the writing of this article.
If you would like to understand more about what demand connection reforms mean for you or your business, please do not hesitate to get in touch.
Junya Ohashi, a lawyer seconded from Nishimura & Asahi in Japan, contributed to the writing of this article.
Partner, Head of Energy Sector, London
Partner, London and Israel Group
Partner, London
Of Counsel, London
Senior Associate, London
Deep expertise. Commercial edge.
The contents of this publication are for reference purposes only and may not be current as at the date of accessing this publication. They do not constitute legal advice and should not be relied upon as such. Specific legal advice about your specific circumstances should always be sought separately before taking any action based on this publication.
© Herbert Smith Freehills Kramer 2026
Receive timely insights and briefings from HSF Kramer, tailored to keep you informed and ahead